Building a pool looks complicated from the outside. It isn't, once someone walks you through it. Here is every stage of a gunite pool build in plain English, from the first dig to the first swim, with the terms you'll hear along the way: steel, gunite, tile, coping, and plaster.

From permit approval to final inspection. Weather, design complexity, and your city's permit office all affect it.
Dig, steel, plumbing, concrete shell, tile and coping, deck, equipment, interior finish, fill, and start-up.
The concrete shell needs roughly four weeks to reach full strength. Tile, coping, and decking happen during that time.
Where a complete new gunite pool with us starts. See the cost guide for what moves the number.
Every pool we build follows the same order. Each step lists what happens, why it matters, and what you'll see in your backyard. Times are typical for the Treasure Valley and vary by project.
We meet at your home and walk the yard. We look at the slope, the soil, where water drains, where utilities run, and how equipment will get in. Then we talk about how you'll use the pool: laps, kids, entertaining, or all three.
From that we draw a plan showing the pool's shape, depth, steps, benches, and features, and we give you an exact price.
Your part: decide what matters most. Size, depth, a spa, and the finishes you pick here drive the cost more than anything later.
Every city in the Treasure Valley requires a building permit for an inground pool. The plan is engineered so the steel and concrete match your soil, then submitted to your city or county. If you have an HOA, its approval usually happens now too.
We handle the permit paperwork for you. Nothing is happening in the yard yet, so this is the stage that feels slowest.
We paint the pool's outline on the ground so you can stand in it and confirm the position. Then an excavator digs the hole to the exact shape and depth of the plan, and trucks haul the dirt away.
This is the loudest, messiest, most exciting day. A section of fence often comes down for access and goes back up later.
Good to know: rock, groundwater, or buried surprises show up here if they're going to. An experienced builder reads the site ahead of time so they rarely are surprises.
Crews tie a cage of steel bars, called rebar, across the floor and up the walls. Concrete is strong when squeezed but weak when pulled or bent. Steel handles the pulling and bending, so the two together make a shell that resists cracking.
This matters more in Idaho than in warm states, because the ground moves a little every winter as it freezes and thaws.
Before any concrete goes in, the pipes do. Plumbers run lines for the drains, the skimmer (the opening that pulls leaves off the surface), the returns (where clean water flows back in), and any spa jets or water features. Pipes are filled with pressurized water or air to prove nothing leaks.
Electricians run conduit for lights and equipment and connect all the metal in and around the pool together, called bonding, which is a key electrical safety step. A city inspector checks this work before we move on.
This is the day the hole becomes a pool. A crew sprays concrete at high pressure through a hose, packing it around the steel to build the floor, walls, steps, and benches as one solid piece. Finishers carve and smooth it by hand as it goes on.
Gunite and shotcrete are both sprayed concrete. The difference is only when the water is added: at the nozzle for gunite, at the plant for shotcrete. Both make an equally strong shell when applied by a skilled crew.
Your part: for the first week or so we'll ask you to hose the shell down a couple of times a day. Concrete that dries slowly ends up stronger.
While the shell cures, the finish work starts. A band of tile is set around the inside at the waterline, and the coping, the cap along the top edge of the pool, is installed.
This is when the pool starts to show its personality. Both are explained in detail below.
The deck is the patio surface around the pool. Crews grade the ground, set forms, and pour concrete or lay pavers or stone. A flexible joint is left between the deck and the coping so each can move on its own through freeze and thaw without cracking the other.
Meanwhile the equipment is set on its pad and connected: the pump, filter, heater, and controls. An automatic cover, if you chose one, is installed around now too.
The interior finish is the smooth, waterproof surface you see and touch: plaster, quartz, or pebble. A crew trowels it onto the cured shell by hand in a single day.
The gray concrete disappears and the pool takes on its final color. The yard needs to be clean first, which is why this is always one of the last steps.
The pool is filled right after the finish goes on, without stopping, so the surface cures evenly under water. Once it's full we start the equipment, balance the water chemistry, and brush the new surface regularly for the first couple of weeks while it hardens.
After the final inspection, we walk you through everything: how to run the equipment, test the water, and look after the pool. Then you swim.
Your part: keep the hose running until the water reaches the middle of the tile, and follow the start-up instructions we give you. The first month of care sets up the finish for years.
These are the decisions that shape how your pool looks and feels. None of them is complicated once you know what each one does.
The concrete shell is strong but rough and slightly porous. The interior finish is a cement-based coating troweled over it that makes the pool watertight, comfortable underfoot, and the color you want. The color of the finish is what gives the water its color.
White cement mixed with fine marble dust. It gives the smooth feel and bright, light-blue water most people picture when they think of a pool.
Plaster with crushed quartz mixed in. Quartz is harder than marble, so the surface resists stains and wear better, and it comes in more colors.
Small rounded stones set in cement. It's the toughest finish and gives a natural, lagoon-like look, with deeper blues and greens available.
How long do they last? Depending on the finish and how well the water chemistry is kept, an interior lasts roughly 8 to 20 years before it needs resurfacing. Resurfacing is a normal part of owning a concrete pool, and the shell underneath is built to outlast many finishes.
The waterline is where sunscreen, body oils, and minerals in the water collect and leave a ring. On plaster that ring stains and is hard to scrub off. On glazed tile it wipes clean. That's why nearly every concrete pool has a band of tile, usually about six inches tall, right where the water surface sits.
Durable, easy to clean, and available in a huge range of colors and patterns. The standard choice for most pools.
Catches the light and shimmers under water. Costs more in both material and labor, so it's often used as an accent on a spa or water feature.
Gives a rustic look that pairs with stone coping. Needs a little more care than glazed tile to keep clean.
The Idaho detail: pool tile here has to be rated for freezing weather. Tile that soaks up water will crack and pop off after a few winters, so the material and the way it's set both matter.
Coping is the cap along the top edge of the pool wall. It finishes the edge, gives swimmers something comfortable to hold, and tips splash water away from the pool toward the deck drains. It's also one of the most visible design choices, because it frames the water.
The deck is poured so it extends over the pool edge in one continuous piece. Simple, modern, and usually the most economical.
Factory-made pieces with a rounded front edge, set one by one. Lots of colors and a tidy, uniform look.
Travertine, flagstone, or similar. Every piece is a little different, and it stays cooler underfoot than many surfaces.
The deck is where you'll spend most of your time out of the water, so think about how you'll use it: a place for chairs, a dining table, room for kids to run. How much deck you build often affects the budget as much as the pool's size.
Concrete brushed while wet for a slip-resistant texture. Practical, durable, and the most affordable.
Concrete pressed with a pattern and tinted to look like stone or tile, at a lower cost than the real thing.
Individual pieces set on a prepared base. Handles ground movement well, and a single piece can be replaced if it's ever damaged.
Pool equipment sits on a small pad, usually tucked beside the house. It does four jobs:
The pump moves the water; the filter traps dirt. A variable-speed pump runs slower for longer and uses far less electricity than older single-speed pumps.
A heater stretches Idaho's swim season. An automatic cover keeps that heat in overnight, cuts evaporation, and keeps debris out.
Chlorine or a salt system keeps the water safe to swim in. Automation lets you run the pump, heat, and lights from a panel or your phone.
For a complete, permitted, swim-ready gunite pool. Spas, water features, premium finishes, larger decks, and difficult sites add to that.
We'd rather tell you that up front than after a site visit. A gunite pool is a permanent structure, engineered for your soil and built by hand over several months. It costs more than a fiberglass or vinyl pool, and it's built to last far longer.
If that range fits, the next step is a free on-site estimate with an exact number. If it's more than you planned, it's still worth a conversation: an owner-assisted build can lower the cost, and if you already have a pool, remodeling is a different budget entirely.
Two reasons. The city has to approve the plan before work starts, and the concrete shell needs about 28 days to reach full strength before the interior finish goes on. The hands-on work in between moves quickly.
No. We need access to the backyard and a few decisions from you at key points, like confirming the layout before we dig. We keep you updated at every stage.
Like a construction site for a while. Expect heavy equipment, dirt, and a temporary gap in the fence. That's why most people finish landscaping after the pool, and why building before the backyard is finished saves money.
Much of the work can continue in cold weather, but concrete and plaster can't be placed in a hard freeze. Winter is the ideal time for design and permits, so construction can start as soon as the weather allows.
If budget is the priority, plaster is a proven choice. If you want more years before resurfacing and don't mind some texture, pebble is the most durable. Quartz sits between them. We'll show you samples of each.
New gunite pool builds with us start at about $105,000. The pool cost guide breaks down what moves the price, and a free on-site estimate gives you an exact figure.
New pool builds start at about $105,000. If that works for you, tell us about your yard and we'll walk the site, answer your questions, and give you an exact number. Free, with no pressure.